・On-site inspection
➡Full property inspection (walls, ceilings, plumbing, electrical and etc).
➡Measured all rooms
※after signed up the contract, construction begun.
・Demolition (5 days) – Remove old interiors and fixtures.
・Plumbing/Utility Work (23 days) – Install new water, gas, and ventilation systems.
・Carpentry (12 days) – Build flooring, walls, ceilings, and frames.
・Electrical Work (3 days) – Install wiring, outlets, switches, and lighting.
・Interior Finishing (6 days) – Wallpaper, flooring, and painting.
・Cleaning (1 day) – Professional cleaning before handover.
・Final Adjustments (1 day) – Final inspection and corrections.